    PERT Calculator

    PERT adds expected times along the critical path, tₑ = (a + 4m + b)/6: these three activities give Te = 15.3333 with an 88.7 % chance of finishing by 17.

    Optimistic a, most likely m and pessimistic b times for each activity on the critical path.

    Expected project duration Te =

    15.3333333333333

    Full answer, then cut to fewer decimals (not rounded):

    • 15.3333333333333
    • 15.333333333333
    • 15.33333333333
    • 15.3333333333
    • 15.333333333
    • 15.33333333
    • 15.3333333
    • 15.333333
    • 15.33333
    • 15.3333
    • 15.333
    • 15.33
    • 15.3
    Project variance σ²
    1.88889
    Project standard deviation σ
    1.37437
    z = (T − Te)/σ
    1.21268
    Probability of finishing by 17
    88.737 %
    Activity times
    Activityambtₑ = (a + 4m + b)/6σ² = ((b − a)/6)²
    124640.444444
    23595.333331
    346860.444444
    Step-by-step solution
    1. tₑ = (a + 4m + b)/6 for each activity; Te = Σtₑ = 15.3333
    2. σ = √Σσ² = √1.88889 = 1.37437
    3. z = (17 − 15.3333) ÷ 1.37437 = 1.21268 → P = 88.737 %

    PERT Formula

    tₑ = (a + 4m + b)/6, σ² = ((b − a)/6)²

    z = (T − Σtₑ)/√Σσ² on the critical path

    Worked Example

    Critical-path activities (2, 4, 6), (3, 5, 9) and (4, 6, 8) with a target of 17:

    1. tₑ = (a + 4m + b)/6 for each activity; Te = Σtₑ = 15.3333
    2. σ = √Σσ² = √1.88889 = 1.37437
    3. z = (17 − 15.3333) ÷ 1.37437 = 1.21268 → P = 88.737 %

    Project standard deviation σ: 1.37437 · z = (T − Te)/σ: 1.21268 · Probability of finishing by 17: 88.737 %

    Activity times
    Activityambtₑ = (a + 4m + b)/6σ² = ((b − a)/6)²
    124640.444444
    23595.333331
    346860.444444

    More Manufacturing and Industrial Engineering Calculators

    Frequently asked questions

    Why is PERT variance added only along the critical path?

    Project duration is the length of the critical path; assuming independent activities, its variance is the sum of their variances.

    What is the difference between PERT and CPM?

    CPM uses one deterministic time per activity; PERT uses three estimates and a beta distribution to give a probability of completion.

    Sources

    Last reviewed: . Factors are stored exactly and computed with 50-digit decimal arithmetic. See how we verify conversion factors.

    Cite this page

    APA

    Scientific Converters. (2026, October 15). PERT Calculator. Retrieved October 25, 2026, from https://scientificconverters.com/calculators/pert-calculator/

    IEEE

    Scientific Converters, "PERT Calculator," scientificconverters.com. Accessed: Oct. 25, 2026. [Online]. Available: https://scientificconverters.com/calculators/pert-calculator/

    Send feedback

    Found a wrong value, a missing unit or an idea? Tell us. We read every message.

    What is it about?

    We store your message, the page you were on and your email if given. See the privacy policy.